Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?

(a)

6 days

(b)

8 days

(c)

10 days

(d)

11 days

Correct Answer

Explanation