Power shortage looms as coal stocks dip, multiple states flock to spot mkt

·

Why in the News

India’s power planning has swung from ruling out fresh coal-based capacity beyond 2022 to a call for 105 to 150 gigawatts (GW) of new coal capacity by 2035. Coal stocks at thermal plants are falling, and the Centre has directed States to secure electricity at all cost before next summer. Several States are now buying power through short-term tenders at very high prices.

What is base-load power, and why is it running short?

  1. What it is: Base-load power is the steady supply that runs round the clock, and in India it comes mainly from coal-based thermal plants. It works like the main water tank that keeps taps running when the rain stops.
  2. Why it matters in the evening: Solar output falls after sunset but summer demand stays high, so thermal plants must carry the evening peak.
  3. What went wrong: Too little base-load thermal capacity and falling coal stocks now threaten a shortage, so the Centre has held high-level meetings.
  4. Timing of the shock: Sporadic rain eased the shortage this year, but a power shock is feared from early next summer.
  5. The takeaway: India has added power capacity, but not enough of the kind that can run on demand after sunset.

How are States and distribution companies responding?

  1. Short-term tenders: At least five States and private distribution companies (discoms) have floated tenders for January to July next year on the Ministry of Power‘s Discovery of Efficient Electricity Price (DEEP) portal. Eg. Tamil Nadu, Kerala, Rajasthan, Gujarat, Noida Power Company Ltd and Adani Electricity Mumbai Ltd.
  2. Election-year demand: Uttar Pradesh is also seeking extra power ahead of its State elections early next year.
  3. Prices above the cap: Some tenders have discovered prices of Rs 19-20 per unit, far above the Rs 10 per unit cap on spot prices in power exchanges.
  4. Costly market segment: Only the High Price Day-Ahead Market (HP-DAM), an exchange segment for costly generation, allows up to Rs 20 per unit.

How low have coal stocks fallen, and how stressed is the grid?

  1. Faster drawdown: Greater reliance on coal-based generation cut plant stocks by about 66% between April and September this year, against about 23% in the same period last year.
  2. Current inventory: Stocks at domestic coal-based plants fell to 20.79 million tonnes (MT) by mid-November, from about 55 MT in early April.
  3. Storage expansion: Plants can now hold about 30 days of coal. The Centre is discussing doubling this to about 60 days, which needs more storage space.
  4. Grid frequency: The grid’s frequency falls when demand outruns supply. Grid India data show it below the mandated lower limit of 49.9 Hz even during solar hours, and lower in the evenings.

Did policy scale down thermal capacity too early?

  1. The earlier plan: The National Electricity Plan (2017-22) effectively ruled out new thermal capacity beyond projects under construction, and focused almost entirely on renewables.
  2. Imported coal discouraged: Policy actively discouraged imported coal projects after global coal prices spiralled.
  3. Renewables without storage: Renewable capacity grew fast without energy storage to carry power past sunset, which is making the grid unstable.
  4. The rethink: The Central Electricity Authority (CEA), the Ministry’s planning body, has called for a reassessment of planned coal additions. Its call for new coal capacity far exceeds the 97 GW now planned.

Challenges

  1. Costly stopgap power: Buying power at double the exchange cap raises discom losses, which pass to consumers or State budgets.
  2. Long build times: New coal plants take years to build, so they cannot meet next summer’s peak.
  3. Storage lag: Without batteries or pumped storage, added solar capacity cannot serve the evening peak.

Way Forward

  1. Plant-wise stock targets: The Ministry of Power should set and track coal stock targets for each plant before summer.
  2. Storage with solar: Tender new solar capacity together with battery or pumped hydro storage.
  3. Peak-based planning: The CEA should plan capacity against evening peak demand, not only against annual energy needs.

Conclusion

India’s power gap now lies less in total capacity than in firm supply after sunset, after planning bet on renewables without storage. Rebuilt coal stocks and supply locked in before next summer’s evening peak will decide whether the shortage is averted.

Key numbers

  1. Coal storage at thermal plants: normative requirement about 59 MT; current capacity up to 80 MT; 160 MT under discussion.
  2. April to September stock fall, last year: 55.2 MT to 42.6 MT.
  3. April to September stock fall, earlier years: 31.8% (2024) and 36.8% (2023).

Matching Previous Year Question

“[2013] Which one among the following industries is the maximum consumer of water in India? (a) Engineering (b) Paper and pulp (c) Textiles (d) Thermal power ANSWER: (d)”

Click here to Download X-Factor Notes for FREE. Cover the entire Microthemes with PYQs.

Download free X-Factor Notes
Revised and updated X-Factor Notes for UPSC Mains 2026: nine subject booklets