💥Mains Ready By December. Smash Mains & Smash PYQ Admissions Open

Subject: Renewable Energy Sector

  • For new energy, remove old bottlenecks

    Why in the News

    India has more than 300 gigawatts (GW) of installed renewable capacity and ranks third globally, yet grid operators curtailed (switched off) a significant amount of solar power between April and June. The causes were transmission constraints and grid security. The Centre’s new Green Energy Corridor Phase-III (GEC-III) will work only if it clears the land, clearance and coordination hurdles that slowed earlier lines.

    What is GEC-III, and why does it focus on lines inside States?

    1. What it is: GEC-III builds lines to evacuate up to 135 GW of renewable power, meaning carry it from plants to consumers, like widening roads out of a busy factory town.
    2. Why it was needed: Rapid solar growth has not made green power available when demand is highest, particularly at the evening peak after sunset.
    3. Storage component: The scheme adds 50 gigawatt-hours (GWh) of battery energy storage. Batteries smooth intermittency, the rise and fall of solar and wind output, and supply power after sunset.
    4. Intra-State focus: Plants cluster in a few regions but demand is spread across each State, so the network’s last leg decides whether green power reaches consumers. Rs 1,36,378 crore is earmarked for transmission.
    5. The takeaway: GEC-III can carry the next phase of India’s green energy transition only if it avoids the bottlenecks that slowed earlier lines.

    Why have transmission lines been slow to build?

    1. Money is not the only hurdle: Past projects show that transmission delays come from approvals on the ground, not only from a shortage of investment.
    2. Right-of-way compensation: The Parliamentary Standing Committee on Energy named right-of-way compensation, payment to landowners when high-voltage lines pass near their property, a major hurdle. Its report was tabled last December.
    3. Land and clearances: The same panel flagged land acquisition and delays in environmental clearances as major hurdles in laying lines.
    4. Fragmented decisions: Separate agencies approve different parts of a line, and the committee found that such fragmented decision-making often delays projects.
    5. Boundaries do not match: Renewable resources, corridors and demand do not follow administrative boundaries, so the Centre and States must plan and implement together.

    What will it take for battery storage to work?

    1. Target versus function: The risk is that storage becomes a procurement target, counted by batteries bought, rather than a working part of the grid.
    2. Four requirements: Battery projects need:
      • viable business models, so storage earns steady revenue;
      • incentives, because the sector relies on overseas suppliers for critical raw materials;
      • recycling arrangements for used batteries;
      • clear rules on who can use storage and who pays for it.

    Challenges

    1. Wildlife conflicts: Overhead lines kill endangered birds, which forces costly rerouting or undergrounding. Eg. The Great Indian Bustard case in Rajasthan and Gujarat.
    2. Weak distribution utilities: Loss-making State power distribution companies (discoms) delay payments, which weakens the case for new intra-State investment.
    3. Slow cell manufacturing: Domestic advanced chemistry cell (battery cell) plants under the Production Linked Incentive (PLI) scheme have been slow to start, so batteries stay imported.

    Way Forward

    1. Single approval portal: The government should act on the committee’s proposal for a portal bringing all approving authorities together for real-time monitoring and faster decisions.
    2. Storage market rules: The Central Electricity Regulatory Commission (CERC) should notify who may use stored power and how it is paid for.
    3. Standard compensation: States should adopt uniform, time-bound right-of-way compensation so landowner disputes settle quickly.
    4. Joint corridor planning: The Central Electricity Authority (CEA) and State transmission utilities should plan corridors together across State boundaries.

    Conclusion

    India’s renewable push has moved from building generating capacity to getting power to consumers when they need it. Whether the single approval portal is set up and storage rules are notified will decide if GEC-III escapes the delays of earlier corridors.

    Matching Previous Year Question

    “[2026] Which of the following statements with regard to Green Hydrogen is/are correct? 1. It is decarbonized hydrogen obtained from natural gas reforming combined with carbon capture and storage (CCS). 2. It is produced using electrolysis of water with electricity generated by renewable energy. 3. National Green Hydrogen Mission of India aims for abatement of nearly 50 MMT of annual greenhouse gas emissions by 2030. (a) 1 only (b) 2 and 3 only (c) 2 only (d) 1, 2 and 3 Answer: B”

  • Green Energy Corridor Phase-III (GEC-III)

    Green Energy Corridor Phase-III (GEC-III)

    Why in the News?

    • The Union Cabinet approved Green Energy Corridor Phase-III (GEC-III) on 30 September 2026 to strengthen the Intra-State Transmission System (InSTS) for renewable energy integration. pasted

    Key Highlights

    • Target: Evacuation of up to 135 GW of renewable energy across States/UTs.
    • Target completion: FY 2032-33.
    • Total project outlay:₹1,86,405 crore.
      • Intra-State Transmission Systems: ₹1,36,378 crore
      • Battery Energy Storage Systems (BESS): ₹50,000 crore
    • Central Financial Support (CFS): ₹54,082 crore.
    • BESS deployment: 50 GWh.
    • Aims to support India’s target of 900 GW installed Non-Fossil capacity by 2035.

    Intra-State Transmission System (InSTS)

    • Focuses on grid integration and power evacuation within States/UTs.
    • Greenfield projects: Implemented through Tariff Based Competitive Bidding (TBCB).
    • Brownfield upgradation/network strengthening: Implemented on Cost Plus Basis (CPB).
    • State Transmission Utilities (STUs): Overall implementing agencies.
    • Transmission Service Providers (TSPs): Participate under TBCB through Build-Own-Operate-Maintain (BOOM) model.

    Battery Energy Storage Systems (BESS)

    • 50 GWh BESS will be deployed.
    • Can be located at:
      • Renewable Energy developer/generator end, or
      • Other locations important for grid flexibility.
    • Addresses:
      • Renewable energy intermittency
      • Grid congestion
      • Peak-hour curtailment
      • Demand during non-solar hours
    • BESS deployment will support the development of the domestic energy storage industry.

    Prelims Quick Revision

    • GEC-III: Approved by Union Cabinet in September 2026.
    • Renewable energy evacuation capacity: 135 GW.
    • BESS deployment: 50 GWh.
    • Total outlay: ₹1,86,405 crore.
    • Central Financial Support: ₹54,082 crore.
    • Target completion: FY 2032-33.
    • Supports 900 GW installed Non-Fossil capacity by 2035.
    • Greenfield = TBCB; Brownfield = CPB.

    UPSC Prelims Trap

    • GEC-III is focused on Intra-State transmission, not solely inter-state transmission.
    • 50 GWh refers to BESS deployment, while 135 GW refers to renewable energy evacuation capacity.
    • TBCB applies to greenfield InSTS projects, whereas CPB applies to brownfield upgradation and network strengthening.
    • STUs are the overall implementing agencies; TSPs participate under the TBCB model.
  • Eye on transmission bottlenecks, Cabinet clears green energy plan

    Why in the News

    For the first time, India’s Green Energy Corridor (GEC) programme will fund battery storage alongside transmission lines, so that solar power is not wasted for want of grid capacity. The Union Cabinet has approved Green Energy Corridor Phase-III (GEC-III) to evacuate up to 135 gigawatts (GW) of renewable energy across States, with completion targeted by FY 2032-33.

    What is GEC-III, and why is it needed?

    1. What it is: GEC-III builds transmission lines and storage to evacuate renewable power, meaning carry it out of solar and wind plants into the grid. It is like widening the roads out of a busy factory town.
    2. Grid bottleneck: Peak power demand keeps hitting record highs, yet grid operators are forced to curtail (switch off) solar generation because transmission lines cannot carry it.
    3. The takeaway: Without new lines and storage, added solar capacity is wasted, so GEC-III is central to the Prime Minister’s stated push towards 900 GW of non-fossil capacity by 2035.

    How large is the transmission gap?

    1. Temporary connections: Close to 21 GW, about 9% of installed renewable capacity, runs on temporary grid connections, awaiting dedicated transmission lines.
    2. Peak-hour limits: Around 12 GW of this faces evacuation restrictions at peak solar hours, so developers lose revenue and several projects’ financial viability is in doubt.
    3. Lost clean power: In FY 2025-26, around 6,900 gigawatt-hours (GWh) of clean electricity faced restrictions because renewable capacity grew faster than transmission.

    What are the components of GEC-III?

    1. Storage at generation, Battery Energy Storage Systems (BESS): 50 GWh of storage at renewable developer or generator sites, or other grid-critical locations, with an outlay of Rs 50,000 crore; primary stakeholder: renewable energy developers and generators.
    2. Evacuation, Intra-State Transmission System (InSTS): New and upgraded intra-State transmission lines, with an outlay of Rs 1,36,378 crore; primary stakeholder: State transmission utilities.
    3. Total outlay: The scheme costs Rs 1,86,405 crore, of which the Centre gives Rs 54,082 crore as central financial assistance (CFA).
    4. Purpose of central support: The CFA offsets intra-State transmission charges, keeping power costs lower for end consumers.
    5. Purpose of storage: Batteries store surplus solar power and release it later:
      • supply stays steady through intermittency, the rise and fall of solar output with sunlight;
      • less power is switched off when lines are congested at peak solar hours;
      • stored power meets demand in non-solar hours.

    How will the projects be built?

    1. Greenfield lines: All new InSTS projects will be awarded through Tariff Based Competitive Bidding (TBCB), where the bidder quoting the lowest tariff wins.
    2. Brownfield upgrades: Upgrading and strengthening existing networks will run on a Cost Plus Basis (CPB), where the utility recovers its approved cost plus a return.
    3. Implementing agency: State transmission utilities will be the overall implementing agency.
    4. Private builders: Transmission service providers (TSPs) will bid under TBCB on a Build-Own-Operate-Maintain (BOOM) model, so they finance, own and run the lines.

    Challenges

    1. Right of way: New lines need land and right-of-way clearance across farms and forests, which often delays transmission projects.
    2. Weak State utility finances: Loss-making State power utilities may struggle to fund their share of the investment.
    3. Battery import dependence: India imports nearly all its lithium and cobalt, so storage costs depend on foreign supply chains.
    4. Timeline mismatch: The scheme runs into the next decade, but renewable capacity is added every year, so curtailment can persist meanwhile.

    Way Forward

    1. Time-bound clearances: States should fix time-bound right-of-way and land approvals for GEC-III lines.
    2. Congested zones first: State transmission utilities should first build lines where plants run on temporary connections.
    3. Domestic battery cells: The Centre should link BESS procurement to domestic cell manufacturing under the Production Linked Incentive (PLI) scheme for advanced chemistry cells.
    4. Transparent bidding: States should publish TBCB awards and completion timelines so private builders stay accountable.

    Conclusion

    GEC-III shifts India’s renewable push from adding capacity to moving and storing the power already produced. Whether State utilities award and finish the lines on time will decide how quickly curtailment falls.

    Matching Previous Year Question

    “[2026] Which of the following statements with regard to Green Hydrogen is/are correct? 1. It is decarbonized hydrogen obtained from natural gas reforming combined with carbon capture and storage (CCS). 2. It is produced using electrolysis of water with electricity generated by renewable energy. 3. National Green Hydrogen Mission of India aims for abatement of nearly 50 MMT of annual greenhouse gas emissions by 2030. (a) 1 only (b) 2 and 3 only (c) 2 only (d) 1, 2 and 3 Answer: B”

  • Farmers need a share of the solar boom

    Why in the News

    India’s solar capacity has grown sixtyfold since 2014 through utilities and rooftop households, but farmers are left out because Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-KUSUM), the Ministry of New and Renewable Energy’s farmer scheme, has lagged. The Indian Council for Research on International Economic Relations (ICRIER) proposes agri-photovoltaics, so farmland yields food and power.

    What is PM-KUSUM Component A, and why has it lagged?

    1. What it is: Component A lets a farmer build a solar plant of up to 2 MW on his land and sell its power, like growing electricity as a crop.
    2. Why it was added: PM-KUSUM began with solar pumps; Component A added income from selling power.
    3. What went wrong: With no capital subsidy, a farmer must raise the full plant cost himself, so the scheme has not yet succeeded.
    4. The takeaway: Farmers hold the land solar needs but not the capital to use it, so the boom has passed them by.

    Who has gained from the solar boom so far?

    1. Global standing: India ranks third in solar, after China and the United States.
    2. Utility scale parks: About 74 percent of capacity sits in large parks on government provided wasteland, run by firms such as NTPC. Eg. Khavda Solar Park, Gujarat.
    3. Rooftop households: Rooftop solar holds about 20 percent, driven by Pradhan Mantri Surya Ghar: Muft Bijli Yojana, whose subsidies cover about 60 percent of a household system.
    4. Finance gap: Surya Ghar has a World Bank loan; PM-KUSUM has none.

    How would agri-photovoltaics bring farmers in?

    1. Agri-photovoltaics: Agri-PV mounts panels about 11 feet above the ground with spacing for crops underneath, so one field yields food and power.
    2. Subsidy and cheap credit: Component A needs a Surya Ghar style subsidy. Farmers and farmer producer companies (FPCs) should get Priority Sector Lending, the cheaper credit banks must give agriculture.
    3. Feed-in tariff: This is the fixed price a distribution company (discom) pays per unit fed into the grid. A tariff of Rs 4.5 per kWh makes projects viable.
    4. Solar cooperatives: The World Bank financed Operation Flood, the dairy cooperative drive, and should back solar cooperatives too. This “PM Surya Khet Kranti” makes solar the “third crop“.

    Why would it pay, and what is the trade-off with food?

    1. Food versus energy: Ground mounted solar on farmland displaces food crops, so the writers want it banned.
    2. Three objectives: Agri-PV under Component A serves three objectives:
      • Farm income: rises eight to ten times, as an ICRIER pilot in Rajasthan showed through power sales and shade tolerant horticulture;
      • Power subsidy bill: falls, because farm power costs about Rs 8.5 per kWh to supply, the Comptroller and Auditor General (CAG) estimates, but farmers pay about Rs 1;
      • Rural industrialisation: clean energy helps rural areas industrialise.
    3. No new spending: A feed-in tariff near half the supply cost can come from the existing farm power subsidy.

    Challenges

    1. Scale of farm demand: Agriculture uses nearly 260,000 GWh a year, priced far below cost, so agri-PV must scale widely to matter.
    2. Discom payment delays: Loss making discoms pay generators late, so power sales are unreliable income.
    3. Rising demand needs storage: Artificial intelligence (AI) data centres consume heavy power, so new solar must come with storage.

    Way Forward

    1. Aggregate through FPCs: Route agri-PV plants through FPCs and cooperatives so small holdings pool land and credit.
    2. Differentiated tariff: State regulators should notify a separate agri-PV feed-in tariff.
    3. Storage in design: Plan agri-PV with battery or pumped hydro storage beyond lithium-ion.

    Conclusion

    India can scale solar, but farmers, who hold most of the land, own almost none of it. Whether Component A gets Surya Ghar style support and a paying tariff will decide if solar also raises rural incomes.

    Key numbers

    1. Solar capacity: 2.82 GW (2014) to 168.04 GW (August 2026); Khavda Solar Park 30 GW.
    2. Surya Ghar: Rs 78,000 central subsidy for 3 kW, plus Rs 30,000 in Uttar Pradesh, against Rs 1.8 lakh cost; 1 crore households; outlay Rs 75,021 crore; World Bank loan $820 million.
    3. ICRIER pilot: 600 kW; income about Rs 40,000 to nearly Rs 4 lakh per acre; Rs 1.4 crore State Bank of India loan, Rs 60 lakh farmer share, Rs 35 lakh Kotak corporate social responsibility funds.
    4. Tariff subsidy bill: Rs 2.35 lakh crore a year; agriculture may bear 85 percent.

    Government initiatives for solar energy

    1. Production Linked Incentive (PLI) scheme: Rewards domestic manufacture of solar cells and modules.
    2. Green Energy Corridors: Transmission lines carrying large solar and wind output into the grid.
    3. Battery storage viability gap funding: Part funds battery storage to steady renewable supply.

    Matching Previous Year Question

    “[2026] Which of the following statements with regard to Green Hydrogen is/are correct? 1. It is decarbonized hydrogen obtained from natural gas reforming combined with carbon capture and storage (CCS). 2. It is produced using electrolysis of water with electricity generated by renewable energy. 3. National Green Hydrogen Mission of India aims for abatement of nearly 50 MMT of annual greenhouse gas emissions by 2030. (a) 1 only (b) 2 and 3 only (c) 2 only (d) 1, 2 and 3 Answer: B”

  • India’s vast canal network offers a land-free path to solar power

    Why in the News

    The Centre has approved the PM Surya Sarovar Yojana (PM-SSY). The scheme aims at developing 5,000 MW of floating solar capacity on reservoirs and other inland water bodies across the country. The approval follows a steady rise in the cost and difficulty of acquiring land for large-scale solar projects. India’s canal network, one of the largest in the world, carries a second land-neutral option in canal-top photovoltaics (CTPV), meaning solar panels mounted on elevated structures built over canal stretches. A 2024 assessment placed India’s combined canal-top and canal-bank potential at around 131 GW. Deployment has stayed limited for more than a decade after the first installation, so the binding constraint on canal-top solar is system cost and structural design rather than resource availability.

    What is canal-top photovoltaics?

    1. Structures built over the canal: CTPV mounts solar panels on specialised structures erected over canal stretches. The canal itself becomes the site, so no separate plot is acquired.
    2. Difference from floating solar: A floating system places panels on floating platforms on a water body. CTPV instead uses elevated structures standing above the canal.
    3. Design set by canal geometry: A system is built to the canal’s width, design and orientation. The elevated structure may span the canal or sit along the canal banks.
    4. Unobstructed water flow: Every design must leave the canal’s water flow unobstructed.

    What does covering a canal deliver beyond electricity?

    1. Land neutrality: CTPV requires virtually no additional land. Eg. In Punjab, the installation of 20 MW of canal-top systems is estimated to have saved nearly 100 acres of land.
    2. Reduced evaporation loss: Panels covering a canal stretch cut the amount of water lost to evaporation. The gain matters most in India’s water-stressed regions.
    3. Cooling effect on panel output: The water beneath the panels cools them. Panel performance in hot weather improves as a result.
    4. Measured dual output: A 1 MW system over the Narmada Canal at Mehsana in Gujarat saves close to 9 million litres of water every year. It generates 1.6 million units of electricity annually.

    How far has deployment actually gone in India?

    1. Early adoption: India’s first canal-top installation was commissioned at Mehsana in Gujarat in 2012. The country was an early adopter of the technology.
    2. Gujarat and Punjab capacity: Two 10 MW systems were commissioned in Vadodara, Gujarat, between 2014 and 2017. Punjab commissioned 20 MW of canal-top systems between 2017 and 2018.
    3. Punjab’s current pipeline: The Punjab Energy Development Agency invited expressions of interest in September 2025 for 40 MW of canal-top projects. The State’s canal network spans over 10,000 km.
    4. Haryana’s exploration: Haryana has initiated efforts to explore canal-top systems over six of its irrigation canals.
    5. A niche after a decade: CTPV remains largely a niche application, and deployment has stayed limited for more than a decade after the first installation.

    What does the assessed potential show about where canal-top solar can scale?

    1. Assessed potential: A 2024 assessment estimated India’s canal-top and canal-bank potential at around 131 GW.
    2. Scope of the estimate: The estimate covers canals up to 30 m wide. It assumes vertical bifacial installations for canals over 30 m wide.
    3. Screening criteria: Solar irradiation, canal characteristics, distance from substations and protected areas were applied to identify the best-suited canal stretches across India.
    4. Leading States: Uttar Pradesh, Bihar, Karnataka, Andhra Pradesh and Punjab carry the highest potential.

    Why has a decade of policy support not converted pilots into scale?

    1. The 2014 pilot scheme: The Ministry of New and Renewable Energy (MNRE) launched a pilot-cum-demonstration scheme for grid-connected canal-top and canal-bank projects in 2014. It set a target of 50 MW each for canal-top and canal-bank projects.
    2. Financial assistance offered: The scheme offered Rs 3 crore per MW for canal-top systems and Rs 1.5 crore per MW for canal-bank systems. The assistance was capped at 30% of project cost, whichever was lower.
    3. Limits of financial assistance: The 2014 scheme shows that financial support by itself does not convert pilots into large-scale deployment.
    4. Floating solar as the new policy signal: PM-SSY is expected to revitalise the floating solar segment and drive its adoption across India. That policy interest in land-neutral solar can extend to canal-top systems.

    Challenges to canal-top photovoltaics

    1. High system cost: Elevated structures spanning a canal need additional structural steel, foundations and access provisions, so canal-top systems cost more than ground-mounted ones. Eg. High system cost is the primary bottleneck behind a deployment record of a few tens of megawatts since 2012.
      The Fix: Route early projects through viability gap funding and low-cost debt, so developers build experience and cost falls through scale and standardisation.
    2. Structural design against canal operations: The structures must avoid disrupting canal operations and must withstand winds. Eg. A design spanning an irrigation canal has to clear the water flow and carry maintenance access at the same time.
      The Fix: Issue standardised specifications and guidelines for canal-top structures, so each developer does not engineer the same span from scratch.
    3. Maintenance on a working canal: Cleaning panels, replacement and repair are difficult on structures elevated above a canal that is in use. Eg. The two 10 MW systems at Vadodara sit over live irrigation canals.
      The Fix: Build operations and maintenance access into the design standard rather than leaving it to each project’s own layout.
    4. Linear layout and evacuation distance: A canal-top system runs along the canal’s course, so irregular paths and changes of direction raise the cost of electricity where substations or transformers are not close. Eg. Punjab’s canal network runs over 10,000 km across the State.
      The Fix: Select and prioritise canal stretches on land scarcity, nearby electricity demand, grid connectivity and canal geometry before capacity is tendered.
    5. Institutional coordination: A canal-top project sits across a State nodal agency and an irrigation department, each with its own approval process. Eg. Haryana’s exploration covers six irrigation canals under its irrigation administration.
      The Fix: Attach capacity building of State nodal agencies and irrigation departments, plus streamlined process flows, to any renewed canal-top scheme.

    Conclusion

    Land-neutral solar has moved from demonstration to a funded national scheme in the floating segment, and canal-top solar sits one step behind it. The obstacle is not the size of the resource or the absence of a subsidy, both of which have been established for years. It is the cost of building over a working canal and the absence of a standard way of doing it. The measure to watch is whether any renewed canal-top support carries standardised specifications and State agency capacity building alongside the money, since money on its own has already been tried once.

    Matching Previous Year Question

    “[2015, GS3, 12.5 marks] To what factors can be the recent dramatic fall in equipment cost and tariff of solar energy be attributed? What implications does the trend have for thermal power producers and related industry?”

  • Heat, weak monsoon continue to push up power demand

    Why in the News

    India’s peak electricity demand touched 269 gigawatt (GW) on September 10, the highest ever recorded for that month and close to the year’s peak of 270 GW set during the summer in May. Demand normally eases by September as the summer heat recedes, and September has recorded the year’s highest peak only twice in recent years, in 2023 to 24 and 2020 to 21. This year persistent heat, a deficient monsoon and higher irrigation load have held consumption at summer levels. The contested point is that the surge is arriving at the hour the grid is weakest, since solar generation falls away in the evening and night when the peak now occurs.

    What is peak power demand?

    1. What it measures: Peak demand is the highest instantaneous load the grid has to meet at any moment in a period, measured in gigawatt, and it sets the capacity the system must keep available.
    2. How it differs from consumption: Total electricity consumption is measured in units of energy over a period, in billion units, and a system can have flat consumption with a sharply higher peak.
    3. Why the distinction matters: Capacity planning, reserve margins and spot market prices are driven by the peak rather than by the total, so a rising peak stresses the system even where annual consumption growth is modest.

    What does the September demand data show?

    1. The record for the month: Peak power demand touched 269 GW on September 10, the highest ever peak recorded for September.
    2. Proximity to the summer peak: The year’s highest peak so far is 270 GW, recorded during the peak summer in May, so September is running within a gigawatt of it.
    3. The normal pattern: Demand usually peaks in April, May, June and July, driven by air conditioners and other cooling appliances in households and commercial establishments, and eases into a post summer pattern by September.
    4. Consumption growth: The Indian Energy Exchange (IEX), the country’s largest power trading platform, puts electricity consumption at 49.84 billion units between September 1 and 9, up 20.7 per cent from the same period a year earlier.

    Why has demand stayed at summer levels?

    1. Heat and cooling load: The Energy and Resources Institute (TERI) attributes the increase to persistent heat and continuing cooling demand, with El Nino related weather conditions adding to it.
    2. Irrigation load: Deficient rainfall raises irrigation demand, so agricultural pumping load rises at the same time as air conditioning load.
    3. The temperature and rainfall forecast: The India Meteorological Department (IMD) had forecast monthly average maximum temperatures in September above normal over most of the country, and rainfall below normal at less than 91 per cent of the long period average.
    4. The rainfall shortfall recorded: Between June 1 and September 9 India received 648 millimetres of rainfall against a normal of 760.6 millimetres, a seasonal deficit of 15 per cent.
    5. A recurring condition: The All India DISCOM Association states that this type of uncertainty will prevail given global warming and the consequential changes in weather and climate.

    Where does the system actually run short?

    1. The daytime surplus: Expansion of solar capacity has left the system comfortable during daylight hours, and grid operators have had to curtail solar generation as the system struggles to absorb the surplus.
    2. The evening and night deficit: Supply conditions tighten in the evening and at night as solar generation falls away, which is when the tightest balance now occurs.
    3. The measured shortfall: Grid India data show a night time shortfall of about 7.7 GW on September 9, when peak demand touched 267 GW, and 6.1 GW on September 10 at the 269 GW peak.

    What is filling the evening gap?

    1. Gas based generation: Electricity generation from gas based plants rose 80.32 per cent during September 1 to 9 over the same period last year, and gas is relatively expensive to run.
    2. Coal at near maximum: Coal based generation over the same nine days rose 25.30 per cent, from 26,135.72 million units in 2025 to 32,748.95 million units in 2026, with plants operating at near maximum levels.
    3. The cumulative coal shift: Since April, coal based generation has risen 10.64 per cent, from 553,730.78 million units to 612,663.37 million units, reflecting heavy reliance on coal through non solar hours.
    4. Hydropower squeezed: Deficient rainfall has cut hydropower generation, which deepens dependence on thermal generation and has pushed up prices in the spot electricity market.

    Challenges to meeting a weather driven evening peak

    1. No storage at the scale of the shortfall: Solar capacity cannot serve an evening peak without storage, and battery capacity on the Indian grid remains small against a shortfall measured in gigawatt. Eg. Grid operators curtailed solar output during the day in the same week the night time shortfall ran above 6 GW.
      The Fix: Tie every new solar tender to a contracted block of storage delivering into the evening peak rather than procuring energy alone.
    2. Expensive peaking generation: The evening gap is bridged with gas, which is the costliest generation in the stack, and the cost lands on distribution companies already carrying losses. Eg. Gas based generation rose sharply in the first nine days of September while spot market prices climbed.
      The Fix: Run a separate capacity market that pays for availability at the peak hour, so peaking plants are financed without distorting the energy price.
    3. Agricultural load is uncontrolled: Irrigation pumping rises with a rainfall deficit and is largely unmetered, so the system cannot shift it away from the peak. Eg. A 15 per cent seasonal rainfall deficit raised irrigation demand at the same time as cooling demand.
      The Fix: Expand segregated agricultural feeders that supply daytime solar power to pumps, moving that load into the surplus hours.
    4. Hydropower is no longer a reliable balancer: Hydropower is the traditional flexible source for an evening peak, and a deficient monsoon removes it in the same season that demand rises. Eg. Reduced reservoir inflows this monsoon have squeezed hydro generation exactly when the peak moved into September.
      The Fix: Contract pumped storage capacity on long term agreements so evening flexibility does not depend on the year’s rainfall.

    Conclusion

    The demand peak has moved out of the summer months and into a season the power system was not planned around, and it has moved into the hours when the fastest growing source of supply produces nothing. The response so far has been to run coal harder and gas more often, which raises both emissions and the spot price. The thing to watch is whether storage procurement is attached to new solar capacity at the scale the evening shortfall now requires, since every further year of weather driven September peaks will be met from the thermal fleet until it is.

    Back2Basics: Grid India

    1. What it is: Grid Controller of India Limited, known as Grid India, is the system operator responsible for integrated operation of the national electricity grid.
    2. What it was before: It was formerly the Power System Operation Corporation Limited, and it functions under the Ministry of Power.
    3. What it runs: It operates the National Load Despatch Centre and the Regional Load Despatch Centres, which balance generation against demand in real time.
    4. Why its data matters here: Scheduling and despatch data from these centres is the source for measured demand met, peak demand and the shortfall at any hour.

    Matching Previous Year Question

    “[2026, GS3, 15 marks] Explain the key challenges for India’s energy security. What measures do you suggest for ensuring energy security along with economic growth and sustainability?”

  • Limits to supply, rising demand: Behind Keralam’s electricity crisis

    Why in the News

    The Keralam State Electricity Board (KSEB) has instituted power cuts lasting between 30 minutes and an hour to manage peak hour demand, including cuts at night. Average daily demand in September 2026 reached about 5,000 MW against 3,794 MW in September 2025, and only 4,200 MW has been met. The shortfall arrives at the hour when the state’s largest renewable asset stops producing, because rooftop solar output ends at dusk and the state has no storage in service. The tension is that a state that leads the country in rooftop solar cannot use any of it against the demand peak that is actually breaking its system.

    How does a State draw power from the Central pool?

    1. What a Central Generating Station is: Central Generating Stations (CGS) are large power generating stations owned centrally rather than by a state utility.
    2. How allocation works: The Union Ministry of Power periodically allocates generation capacity to states from its pool of unallocated quota in those stations.
    3. Who has jurisdiction over electricity: Electricity is a subject on the Concurrent List of the Constitution, so both the Centre and the states have jurisdiction over it.

    How large is the shortfall?

    1. Demand has risen sharply in a year: Average daily demand in September 2026 was about 5,000 MW, against 3,794 MW in September 2025.
    2. Supply has not kept pace: The state has met only 4,200 MW, leaving a daily shortage.
    3. Own generation and the Central pool draw: Keralam produces only 1,650 MW and draws 1,500 MW from the Central pool.
    4. The structural position: The state generates only 25 per cent of its actual requirement from all sources including hydel, solar and wind, against 86 per cent for Andhra Pradesh and 50 per cent for Tamil Nadu.

    Why has hydropower been throttled?

    1. The monsoon failed: The southwest monsoon was weak through the June to September period, with Keralam recording a 26 per cent deficit in seasonal rainfall till 11 September.
    2. The El Nino effect: The El Nino effect, meaning the abnormal warming of surface waters in the equatorial Pacific Ocean that can suppress the Indian monsoon, has been witnessed this year.
    3. Reservoir water storage: Water storage across all KSEB reservoirs stood at only 63.75 per cent of the maximum storage level as of 10 September.
    4. The Board is rationing water, not power alone: KSEB has throttled down hydropower generation deliberately, holding storage against the withdrawal of the monsoon and higher temperatures in the weeks ahead.

    Why does rooftop solar not close the night gap?

    1. The state leads on rooftop capacity: Keralam’s solar production hit 2,508 MW by the end of May, with the vast majority of it rooftop panels.
    2. The scheme behind the build: Under PM Surya Ghar, Keralam has 2.96 lakh installations covering 3,03,531 households.
    3. The output arrives at the wrong hour: Solar power does not help meet the nighttime demand, because the state has no options to store it.
    4. The storage is contracted but not running: KSEB has lined up a slew of Battery Energy Storage Systems (BESS) that are yet to become operational.

    What is a Battery Energy Storage System?

    1. The battery and its grid electronics: A bank of rechargeable cells with power electronics attached to the grid. It charges when generation exceeds demand and discharges when demand exceeds generation, so energy produced in one hour is delivered in another.
    2. Time shifting of solar output: Solar output peaks near midday and ends at dusk, while the demand peak sits in the evening. A battery moves the midday surplus into the evening block, which is the only route by which a daytime resource serves a night peak.
    3. Ramping, not only energy: A battery responds within seconds, so it also covers the sunset ramp, the period when solar falls away faster than thermal or hydro plants can raise their output.
    4. The limits of stored duration: A battery holds a fixed quantity of energy and delivers it for a defined duration, commonly a few hours. It shifts a peak rather than adding generating capacity, and it supplies nothing that was not generated and stored first.

    Why is night demand rising?

    1. The consumer mix loads the evening: Domestic consumers make up 75 per cent of the state’s power connections, so demand rises at night rather than during working hours.
    2. Temperatures are abnormally high: The state disaster management authority has put Keralam on alert for an unusual rise in temperature, with a departure of up to 4 degrees Celsius from normal.
    3. Cooling load runs longer: Rising night temperatures are driving long duration air conditioner usage.
    4. Electric vehicle charging: KSEB has found that nighttime demand is also rising owing to the charging of electric vehicles.

    Challenges to Keralam’s power supply security

    1. Buying from the exchange fails when the scarcity is national: A deficit state can outbid others only when surplus exists somewhere, and this September the shortage is countrywide. Eg. India is witnessing an unusual surge in electricity demand this September, with peak power demand nearing the level recorded during peak summer, driven by a poor monsoon and low coal stock at power plants.
      The Fix: Contract firm capacity ahead of the season under medium term agreements, so the state is not bidding into a national spot market at the moment of scarcity.
    2. The coal fleet has no headroom to absorb the gap: Thermal plants are the swing capacity a deficit state usually leans on, and they are already running close to their limits. Eg. The plant load factor of most imported coal based plants is around 70 per cent or above, leaving no thermal plant that can be asked to raise generation.
      The Fix: Shift a defined share of the evening block onto demand response contracts with large consumers, so the peak is reduced rather than sourced.
    3. Nothing firm replaces solar at the evening ramp: The system loses its entire solar output within an hour of sunset, which is also the hour demand rises, and only fast ramping capacity can bridge that. Eg. Nationally, generation from gas based plants rose 80.3 per cent during 1 to 9 September over the same period last year, with the Centre relying on 4.5 to 5.5 GW of gas based capacity to meet the evening shortfall.
      The Fix: Bring the Board’s contracted battery systems into service against a dated commissioning schedule, since they are the only asset that can move midday solar into the evening block.
    4. Distributed solar weakens the utility that must still serve the peak: A rooftop consumer exports at midday and draws at night, so the utility recovers less revenue while carrying the same obligation to supply at the peak. Eg. Keralam’s rooftop capacity is concentrated in domestic connections, which are the same consumers driving the night peak.
      The Fix: Move rooftop settlement from net metering to net billing with a time of day price, so midday export and evening drawal are valued at what each is actually worth to the system.

    Conclusion

    The immediate crisis will ease when the monsoon withdrawal passes and temperatures fall, and the Board’s rationing is calibrated to hold storage until then. What will not change on its own is the structural position, because a state generating a quarter of its own requirement is buying the rest in a market that tightens in exactly the months it needs power most. The measurable marker is the commissioning of the contracted battery systems, since until they run, every additional megawatt of rooftop solar adds to the state’s daytime surplus and nothing to its evening deficit.

    Back2Basics: PM Surya Ghar Muft Bijli Yojana

    1. PM Surya Ghar: Muft Bijli Yojana: A central scheme under the Ministry of New and Renewable Energy to install rooftop solar systems on residential buildings.
    2. Coverage target: One crore households, with free electricity of up to 300 units a month for the households that install under it.
    3. Household financing route: Central financial assistance is credited directly to the beneficiary’s bank account, alongside access to collateral free low interest loans for the balance cost.
    4. Capacity building component: The scheme carries a capacity building component covering training in installation, operation, maintenance and repair of rooftop systems at the local level.

    Matching Previous Year Question

    “[2025] Consider the following statements about ‘PM Surya Ghar Muft Bijli Yojana’: I. It targets installation of one crore solar rooftop panels in the residential sector. II. The Ministry of New and Renewable Energy aims to impart training on installation, operation, maintenance and repairs of solar rooftop systems at grassroot levels. III. It aims to create more than three lakhs skilled manpower through fresh skilling and up-skilling, under scheme component of capacity building. Which of the statements given above are correct? (a) I and II only (b) I and III only (c) II and III only (d) I, II and III ANSWER: (d)”

  • Small Hydro Power positioned as distinctive in the clean energy transition [MENTION]

    PIB class: Press Release. Ministry: Ministry of New and Renewable Energy.

    Why in News

    The renewable energy ministry stated that Small Hydro Power (SHP) holds a distinctive role in India’s clean energy transition.

    Static Context (the exam value sits here)

    1. Small Hydro Power (SHP) is defined by installed capacity up to 25 megawatts in India. The nodal ministry is the Ministry of New and Renewable Energy (MNRE).
    2. The capacity classes are standardised. Micro is up to 100 kilowatts. Mini is 100 kilowatts to 2 megawatts. Small is 2 to 25 megawatts.
    3. SHP is a run of river resource in most Indian sites. It needs no large reservoir, so its submergence and displacement footprint is small.
    4. SHP counts inside India’s non fossil capacity target. It supports decentralised generation in hill and remote areas.

    Prelims angle

    The 25 megawatt ceiling that defines SHP in India. The nodal ministry MNRE. SHP as a renewable source distinct from large hydro, which the power ministry handles. Run of river design.

    Mains angle

    GS3, infrastructure and energy. Role of decentralised renewable sources in the energy transition and in hill state electrification.

    Matching Previous Year Question

    “[2013, GS3, 5 marks] What do you understand by run of the river hydroelectricity project? How is it different from any other hydroelectricity project?”

  • India’s data centre boom is colliding with its climate reality

    Why in the News

    India’s data centre capacity is set to grow from about 1.5 gigawatts (GW) today to 6.5 GW by 2030, a fourfold expansion in four years, on investment the government estimates at nearly $200 billion over the coming decade. Google, Meta, Amazon and Microsoft have committed billions to build facilities, and States are competing for them with tax exemptions, cheap land and duty waivers. No policy document at the Central or State level has assessed what guaranteed power costs a grid already strained under 45 degree Celsius heat, where cooling water will come from, or what the thermal load of thousands of servers does to regions already near dangerous temperatures. The tension is that the facilities are clustering in exactly the regions where water and grid stress are most acute, and State policies attach almost no conditions to the incentives they offer.

    Why is the scale of the build-out itself the problem?

    1. A fourfold expansion in four years: Capacity nearly tripled from 520 megawatts (MW) in 2020 to nearly 1.5 GW today. The 6.5 GW projected for 2030 compresses the next round of growth into four years.
    2. Electricity demand more than quadruples: Demand from data centres is expected to rise from about 13 terawatt-hours (TWh) in 2024 to roughly 57 TWh by 2030. The Union Ministry of Power estimates that artificial intelligence alone will add 26.3 GW of new demand by 2031-32.
    3. States compete on incentives, not conditions: Maharashtra wants to be the data centre capital. Telangana has declared data centres “essential services”. Karnataka is reviewing its policy to attract more, and Rajasthan is offering tax exemptions and cheap land.

    Why does data centre water use collide with groundwater stress?

    1. The volume per facility: A 100 MW data centre consumes about 2 million litres of water daily, equal to the daily use of roughly 6,500 households. India’s data centres consumed an estimated 150 billion litres in 2024-25, projected to more than double to 358 billion litres annually by 2030.
    2. Clustering in the most stressed regions: Rajasthan extracts 147.11 per cent of its annual groundwater recharge, the second highest rate in the country. Several groundwater assessment units in Maharashtra are classified as semi-critical. Telangana’s Irrigation Minister confirmed in May 2026 that 16 districts were under groundwater stress.
    3. Cities already rationing: Hyderabad’s surface water supply dropped 20 per cent in the summer of 2024 on poor monsoon recharge, forcing the water board to ration supply. Mumbai’s reservoirs stood at 44.5 per cent of capacity in March 2026.
    4. Unaccounted in every State policy: No State policy requires public disclosure of daily water consumption. None requires a hydrogeological assessment before approval. None mandates that water sourcing must not compete with agriculture or municipal supply.

    Why can the grid not deliver the power the boom needs?

    1. Record peaks and interconnection queues: Maharashtra’s peak demand hit 27,230 MW in April 2026, the highest ever handled by the State utility. Two-year waits for 220 kV grid interconnections across the country are lengthening project timelines.
    2. Renewable power is being thrown away: India curtailed 300 gigawatt-hours of renewable energy in the first quarter of 2026 alone because the grid could not carry it, per an Ember Energy analysis of Central Electricity Authority data. Over five years India has met only about 80 per cent of its annual transmission targets, one in four major transmission schemes runs a year or more behind schedule, and 20 GW of renewable capacity faces connectivity delays of more than four months.
    3. Wires lag panels: Rajasthan and Gujarat house the bulk of utility-scale solar and wind. Both face the longest queues at pooling stations (substations where several renewable plants aggregate output before it enters the transmission grid). Solar projects are being built faster than the lines to carry their power.
    4. The coal default: Data centres need reliable, uninterrupted electricity. If renewable power cannot reach them, the power comes from coal, adding to the emissions India is trying to curtail.

    How do data centres make their surroundings hotter?

    1. The satellite evidence: A March 2026 University of Cambridge study of 20 years of NASA satellite data found that data centres raise land surface temperatures by an average of 2 degree Celsius within a 10 km radius, with extreme cases reaching 9.1 degree Celsius. About 340 million people globally live within these affected zones.
    2. Indian cities are already at the edge: Mumbai’s land surface temperature rose from 40.9 degree Celsius in 2003 to 47.3 degree Celsius in 2023, driven largely by urbanisation and heat-trapping infrastructure. Hyderabad’s urban heat island intensity ranges from 5.74 to 6.82 degree Celsius, its urban area doubled between 2001 and 2020, and it recorded temperatures above 43 degree Celsius in the summer of 2024.
    3. The feedback loop: Data centres generate heat, and that heat raises ambient temperature. Higher ambient temperature increases cooling demand. Higher cooling demand raises electricity consumption. Unless that electricity is fully renewable, emissions rise and feed the climate change that is making India hotter.

    Do State policies ask for anything in return for their incentives?

    1. Generous on incentives: State policies offer electricity duty exemptions, transmission charge waivers, stamp duty relief and fast-track clearances.
    2. Silent on conditions: None of the major State policies requires a grid impact assessment before commissioning, mandatory renewable energy sourcing, or a thermal load assessment for surrounding communities.
    3. Telangana guarantees power in a stressed State: The “essential services” classification guarantees data centres uninterrupted power even during shortages, in a State where 16 districts face groundwater stress and temperatures have reached 47 degree Celsius.
    4. Maharashtra diluted its own mandate: The State’s policy originally required 100 per cent renewable energy for core operations. In June 2026 it cut the requirement to 51 per cent, framed as improving project viability.
    5. The exceptions, and their limit: Gujarat’s Data Centre Policy 2026-29 mandates at least 51 per cent green energy sourcing. Karnataka’s IT Minister told the Assembly in March 2026 that the State was reviewing its policy over water and energy concerns, and Tamil Nadu has linked incentives to renewable compliance. Even where mandates exist, enforcement and verification remain weak.

    Why is the constraint market design rather than generation capacity?

    1. Capacity is not the bottleneck: The Union Ministry of Power holds that India’s generation pipeline can absorb the additional demand from data centres. The constraint is market design and transmission infrastructure.
    2. Price grid services separately: The Council on Energy, Environment and Water (CEEW) argues for climate-intelligent power markets in which short-term markets pay separately for ramping, storage and demand response.
    3. Storage at the pooling station: Ember calculates that roughly 3 to 4 GW of two-hour battery storage at renewable pooling stations could have absorbed most of the generation curtailed in early 2026. The technical pieces exist; the gap is regulatory and commercial.

    What should a national sustainability framework contain?

    1. Enforceable use standards: CEEW proposes phased power and water use standards with enforceable benchmarks, and a national AI Energy Star rating that lets buyers and regulators compare how energy efficient a facility or model actually is.
    2. Who pays for the grid: The Institute for Energy Economics and Financial Analysis (IEEFA) warns that a significant part of the associated infrastructure cost could be socialised. Where wider grid infrastructure is required, government support or dedicated financing should stop the cost being passed to consumers through higher tariffs.
    3. Siting away from stressed hubs: IEEFA points to coastal locations. These offer proximity to near-shore wind and solar, and seawater cooling without desalination. Most facilities instead cluster around Mumbai, Hyderabad, Bengaluru and the National Capital Region, where water and grid stress are most acute.
    4. Four minimum standards: A national framework would set minimum standards for renewable energy sourcing, water consumption disclosure, grid impact assessment and thermal load evaluation. It would give investors one set of expectations and consumers one set of protections, on the premise that environmental constraints are economic constraints.

    Challenges to a national data centre framework

    1. Split jurisdiction: Water is a State List subject and electricity sits on the Concurrent List, so a Central standard on water sourcing or grid impact binds no State unless the State adopts it. Eg. The Ministry of Electronics and Information Technology’s draft National Data Centre Policy of 2020 addressed infrastructure status and single-window clearance, not resource standards.
      The Fix: Route the standards through the Central Electricity Authority’s technical standards and the Bureau of Energy Efficiency, which already bind connected consumers, and tie Central incentive money to State adoption.
    2. Mandates without metering: A renewable sourcing mandate is only as good as the verification behind it, and discoms already miss the obligations they carry. Eg. State distribution companies have missed Renewable Purchase Obligation targets for years, forcing the Ministry of New and Renewable Energy to renotify trajectories.
      The Fix: Require third-party audited reporting of power usage effectiveness and water usage effectiveness (ratios of total facility energy and water to that used by computing equipment) as a condition of every incentive.
    3. Cooling technology is a trade-off, not a free fix: Liquid and immersion cooling cut water use but raise capital cost and still dump heat locally. Eg. Evaporative cooling, the cheapest option at 45 degree Celsius, is also the most water intensive.
      The Fix: Set the water standard by climate zone rather than one national number, so a coastal seawater-cooled site and an inland Rajasthan site face different limits.

    Conclusion

    The data centres will be built, and the only open question is on whose terms. The unresolved tension is between States competing on incentives and a resource base that no State policy has been made to account for. What to watch is whether the Centre converts the four standards, renewable sourcing, water disclosure, grid impact and thermal load, into an enforceable national framework before the projected capacity is locked in. The nearer marker is whether Karnataka’s policy review produces conditions or only more incentives.

    Back2Basics

    1. Urban heat island: An urban heat island is the difference in temperature between a built-up city and its rural surroundings, caused by concrete, asphalt and roofs absorbing and re-emitting heat that vegetation and soil would have released through evaporation.
    2. Intensity: Its intensity is that temperature gap in degrees, so Hyderabad’s 5.74 to 6.82 degree Celsius means the city runs that much hotter than its surroundings at the same hour.
    3. Why data centres add to it: Servers convert almost all the electricity they draw into heat, and cooling systems reject that heat into the surrounding air or water, so a large facility acts as a fixed heat source inside the island.

    “[2026] Which of the following statements with regard to Green Hydrogen is/are correct?

    1. It is decarbonized hydrogen obtained from natural gas reforming combined with carbon capture and storage (CCS).

    2. It is produced using electrolysis of water with electricity generated by renewable energy.

    3. National Green Hydrogen Mission of India aims for abatement of nearly 50 MMT of annual greenhouse gas emissions by 2030.

    (a) 1 only (b) 2 and 3 only (c) 2 only (d) 1, 2 and 3

  • Transmission Constraints Emerge as the Binding Limit on India’s Renewable Expansion

    Why in the News

    Insufficient transmission lines have emerged as a major obstacle to India’s renewable energy expansion, with many solar projects being curtailed during daylight hours, a rating agency assessment released on 19 August 2026 found. The constraint has shifted the binding limit on India’s energy transition from how fast capacity can be built to how much of it the grid can actually carry, and new project bidding has collapsed in response.

    What is curtailment of renewable power?

    1. Forced reduction of output: Curtailment occurs when a power generator is forced to reduce or stop producing electricity because of oversupply and grid congestion, even though the plant is capable of generating.
    2. Why solar is hit hardest: Solar output peaks in the middle of the day, when several projects on the same corridor feed in simultaneously and demand is not correspondingly high, so the surplus cannot be evacuated.
    3. What it costs the generator: A curtailed unit is generation permanently lost, since sunlight cannot be stored without additional storage capacity, and the fixed cost of the asset continues to accrue against a smaller output.
    4. Scale of the problem: Around 37% of renewable energy capacity at substations affected by curtailment in the northern, western and southern regions operates under short term access arrangements, and this capacity faces 30% to 50% curtailment during the day.

    What is Temporary General Network Access?

    1. Short term use of spare grid capacity: Temporary General Network Access (T-GNA) is a short term arrangement that allows a renewable energy project to use available capacity on the inter-State transmission system, typically for periods ranging from a single time block to about 11 months.
    2. Why it is precarious: T-GNA gives no firm entitlement to evacuate power, so projects operating under it are particularly vulnerable to curtailment, which raises their operational costs and, on prolonged use, reduces the supplier’s revenues.

    What is the inter-State transmission system?

    1. The national transmission backbone: The inter-State transmission system is the network of high voltage lines and substations that carries power across State boundaries, planned centrally and operated as a single national grid, on which access rights are allotted separately from generation approvals.

    What is a Power Purchase Agreement?

    1. The contract that makes a project bankable: A Power Purchase Agreement (PPA) is the long term contract under which a distribution company or intermediary agrees to buy a defined quantity of power from a generator at an agreed tariff, and without a signed PPA a project has no assured revenue stream against which lenders will disburse.

    What is firm and dispatchable renewable energy?

    1. Renewable power with an assured supply obligation: Firm and dispatchable renewable energy (FDRE) is renewable generation contracted with an obligation to supply a specified quantum during specified hours, achieved by combining solar, wind and storage, so that the buyer receives a guaranteed profile rather than whatever the weather delivers.

    What is round the clock renewable power?

    1. Renewable supply across all 24 hours: Round the clock (RTC) power is a contracting structure in which the developer commits to supply renewable energy across every hour of the day at a specified availability, again by combining complementary sources with storage.

    How severe is the curtailment, region by region?

    1. The affected regions: Curtailment at substations has been recorded in the northern, western and southern regions, the three regions carrying the bulk of India’s solar and wind capacity.
    2. Share on temporary access: Around 37% of renewable capacity at affected substations across these three regions operates under T-GNA.
    3. The daily loss: Capacity operating under T-GNA faces 30% to 50% curtailment during daylight hours.
    4. Western region: About 55% of the affected capacity in western India was under T-GNA, and peak curtailment reached 8,617 MW as of 6 August 2026.
    5. Northern region: The corresponding peak curtailment figure for the northern region was 5,573 MW.
    6. What the concentration means: The western region, which hosts the largest solar and wind clusters, is also the region most dependent on temporary access, so the two vulnerabilities compound rather than offset.

    Why has new capacity bidding collapsed even as construction continues?

    1. Construction pipeline remains large: More than 150 GW of renewable projects were under construction as of 30 June 2026.
    2. Awards have fallen sharply: After 40.6 GW was awarded in 2024-25, awards fell to 14.7 GW in 2025-26 and stood at only 4.7 GW through 10 August 2026.
    3. Contracts awarded but not signed: Between 40 GW and 45 GW of capacity with bids already awarded remained without signed PPAs as of April 2026.
    4. Delays in firming PPAs: Delays in converting awarded bids into signed PPAs are identified as an impediment independent of the transmission constraint.
    5. Land acquisition: Land acquisition for both generation sites and transmission corridors continues to stall projects.
    6. Distribution company finances: The financial position of distribution companies limits their willingness to sign long term purchase obligations at all, since a new PPA adds a fixed payment liability to a stressed balance sheet.
    7. The bidding mix is changing: New bidding is shifting toward firm and dispatchable renewable energy and round the clock power, which require storage and therefore carry a higher tariff than plain solar.

    Is the binding constraint on India’s energy transition generation capacity or grid capacity?

    1. The generation side is not the problem: More than 150 GW is under construction and renewable energy including large hydro is projected to account for more than 35% of electricity generation by 2029-30, against 22% in 2024-25.
    2. The evacuation side is: Capacity is being commissioned faster than transmission corridors are being built, which is why up to half of the output of projects on temporary access is being discarded during the hours it is generated.
    3. The market has already priced the constraint: New awards fell from 40.6 GW to 4.7 GW in eighteen months, which is the developer response to a corridor that cannot carry what is already built.
    4. Storage is the second missing input: Timely execution of intra-State and inter-State transmission infrastructure, along with greater storage capacity, is identified as critical to sustaining renewable additions, because a line that is congested at noon is idle at night.
    5. Why this reframes the target: A target expressed in installed capacity measures what has been built, while a target expressed in share of generation measures what actually reaches consumers, and curtailment is precisely the gap between the two.

    How is transmission and renewable infrastructure financed in India?

    Source: Backgrounder, Infrastructure Financing.docx

    1. Why bank lending failed: Commercial banks funded 25 to 30 year infrastructure assets with one to three year deposits, and this asset liability mismatch produced stressed assets crossing Rs 10 lakh crore in Indian banking by 2017.
    2. National Bank for Financing Infrastructure and Development: Established in 2021 under a dedicated Act of Parliament as India’s first dedicated infrastructure development finance institution, providing non recourse long term financing with 20 to 30 year tenors that match infrastructure asset life.
    3. Its scale: As of December 2025 it had sanctioned approximately Rs 3.03 lakh crore and disbursed approximately Rs 1.09 lakh crore.
    4. Partial Credit Enhancement: It partially guarantees bonds issued by infrastructure companies and special purpose vehicles, upgrading their credit rating from BBB to AA or AAA so that insurance companies and pension funds can participate, with the first such facility sanctioned in February 2026.
    5. Sector specific development finance institutions: REC and PFC finance power generation, transmission and distribution by raising long term bonds and lending to State electricity boards and private power companies.
    6. POWERGRID InvIT: The first Infrastructure Investment Trust in the power sector, set up in 2020, with proceeds channelled into new and under construction transmission projects.
    7. How an InvIT recycles capital: The sponsor transfers only the right to collect revenues for a defined concession period and receives upfront capital which it reinvests in new projects, while ownership is never transferred and the asset reverts at the end of the concession.
    8. The SEBI safeguard: SEBI requires a minimum of 80% of InvIT assets to be in completed operational projects, which protects investors from construction risk, and InvITs may raise debt up to 49% of asset value.
    9. Infrastructure Risk Guarantee Fund: Announced in the 2026-27 Budget, it provides partial guarantees to lenders financing infrastructure projects, covering a portion of the loss on default so that lenders extend credit where they previously refused, while the partial cover preserves due diligence incentives.
    10. Sovereign green bonds: Issued by the Government of India since 2022-23 with proceeds ring fenced for renewable energy, clean transport and sustainable water management, establishing a sovereign benchmark for long term green paper.
    11. The recycling logic: The architecture is designed so that the government builds, the asset stabilises and generates revenue, the asset is monetised through an InvIT, and the capital returns to fund the next tranche of the National Infrastructure Pipeline without a fresh budget allocation each cycle.
    12. Monetisation targets: The National Monetisation Pipeline 2.0, announced in February 2026, targets Rs 16.72 lakh crore including private sector investment of Rs 5.8 lakh crore over 2025-26 to 2029-30, nearly three times the first pipeline’s target.

    Challenges to India’s Renewable Energy Expansion

    1. Transmission build lags generation build: A solar park can be commissioned in about a year while a high voltage corridor takes several years, so the two cannot be commissioned in step. e.g. peak curtailment in western India reached 8,617 MW as of 6 August 2026 on capacity that was already generating.
    2. Temporary access gives no firm evacuation right: Projects on T-GNA can be curtailed at the system operator’s discretion, which makes their revenue unpredictable and their debt harder to service. e.g. around 37% of affected capacity across three regions runs on T-GNA and faces 30% to 50% daytime curtailment.
    3. Storage capacity is inadequate to absorb the midday surplus: Without batteries or pumped hydro the same corridor is congested at noon and underused at night. e.g. the shift in new bidding toward firm and dispatchable and round the clock contracts is itself an admission that plain solar without storage no longer clears.
    4. Distribution company finances limit offtake: Loss making distribution utilities avoid signing new long term purchase obligations irrespective of tariff. e.g. 40 GW to 45 GW of awarded capacity remained without signed PPAs as of April 2026.
    5. Right of way and land acquisition for transmission corridors: Transmission lines cross many districts and require sustained land and forest clearances along the whole route. e.g. land acquisition is named alongside transmission constraints as an independent impediment to project completion.
    6. Geographic concentration of resource: Solar and wind resources are concentrated in a few States while demand centres lie elsewhere, so the transition is dependent on long distance evacuation. e.g. the western and northern regions together account for the two largest curtailment figures recorded.
    7. Tariff pressure from cheap early bids: Projects awarded at very low tariffs in earlier competitive rounds have thin margins that curtailment erases entirely. e.g. the collapse of awards from 40.6 GW in 2024-25 to 4.7 GW through August 2026 shows developers withdrawing rather than bidding lower.
    8. Grid stability with high variable renewable share: A grid carrying more than 35% renewable generation needs inertia, frequency response and balancing reserves that thermal plants currently supply. e.g. must run thermal capacity has to be retained and paid for even as it operates at low plant load factors.
    9. Module and cell supply chain dependence: Domestic content requirements raise capital costs while imported modules expose projects to trade policy shocks. e.g. changes in duty on imported solar cells and modules have repeatedly reset project economics after bids were submitted.
    10. Delayed payments to generators: Payment delays by distribution utilities strain developer working capital independently of curtailment. e.g. the late payment surcharge rules had to be framed specifically to enforce a payment discipline that contracts alone did not achieve.

    Conclusion

    India’s renewable programme has moved past the point where generation capacity is the constraint, and the evidence for that is a 150 GW construction pipeline coexisting with up to 50% daytime curtailment on capacity that is already running. The market has responded not by building more but by bidding less, with awards falling from 40.6 GW to 4.7 GW in eighteen months, and by shifting toward firm and dispatchable contracts that price the constraint into the tariff. Whether renewable energy reaches more than 35% of generation by 2029-30 now depends on the execution of intra-State and inter-State transmission lines and on storage capacity, not on the pace of solar commissioning.

    “[2022, GS3, 15 marks] Do you think India will meet 50 percent of its energy needs from renewable energy by 2030 ? Justify your answer. How will the shift of subsidies from fossil fuels to renewables help achieve the above objective? Explain.”